Step 1: Inital On-Site Consultation
  • Project evaluation
  • In-depth company overview
  • Design discussion
  • Preliminary estimate
Step 2: Secondary On-Site Consultation
  • Estimate review
  • Job site measurements and photos
  • Detailed in-take list
  • Design retainer is collected, if applicable
Step 3: Design & Bidding Process
  • Preliminary plans are created
  • Design review
  • Plans are modified
  • Final plan and bid are presented
  • Construction deposit is collected and contract signed
Step 4: Materials Selection
  • Finalizing details—lighting, appliances, and design materials
Step 5: Pre-Construction Meeting
  • Pre-construction review of all documents, plan and drawings with client
  • Trade partner introduction
Step 6: Project Implementation
  • Construction begins
  • Continuous interaction with client on job progress
Step 7: Project Completion
  • Final punch list
  • Final clean suitable for move-in
Step 8: Warranty
  • Warranty follow-up

Have more questions?